Types of Building Defects
- 1 Major structural defects: affecting load-bearing elements — most serious category, longer statutory warranty period
- 2 Non-major defects: cosmetic or functional issues not affecting structural integrity
- 3 Examples: cracking walls, roof leaks, waterproofing failures, defective glazing, incomplete works, substandard workmanship
Statutory Warranty Periods
- 1 NSW: 2 years for non-major defects, 6 years for major structural defects (from completion date)
- 2 VIC: 2 years for non-structural, 6 years for structural defects under DBI insurance
- 3 QLD: 1 year maintenance period + 6 years for defective work from QBCC
- 4 WA: 12 months maintenance, 6 years for structural defects
- 5 SA, TAS, NT, ACT: Varying periods — check with your state's building regulator
Documenting Defects
- 1 Photograph all defects with timestamps and measuring tape for scale
- 2 Write a detailed defect schedule: location, description, when first noticed
- 3 Get an independent building inspection report from a licensed inspector
- 4 Obtain a rectification cost estimate from an alternative contractor
- 5 Keep copies of all correspondence with the original builder
The Rectification Process
Give the original builder first right to rectify — in writing, with a reasonable timeframe (typically 20 business days). If they refuse or the rectification is inadequate, escalate to your state's building dispute body. Pursuing rectification costs through home warranty insurance requires demonstrating the builder has refused to act or is no longer trading.
⚠️ Watch out: Never allow a builder to rectify defects without inspecting the completed rectification work with a building inspector. Defect rectification is sometimes done superficially, masking rather than fixing the underlying cause.